Launch ITMS as a pilot at 1 SAPL location to validate real-world fit before org-wide rollout. Goal of the pilot: learn what changes are required — in workflows, data model, and UX — when real IT staff and real assets/tickets replace the prototype seed.
Pilot scope (1 location)
Pick pilot location + pilot users (suggest Santosh + Vishal + 1-2 floor IT staff)
Import real asset inventory for that location into CMDB (replaces seed data)
Define ticket categories/priorities to match location's actual IT issues
Run live: all IT issues at that location go through ITMS only (no parallel tracking)
CMDB edges: record real switch → server → ticket dependencies
What we're testing (success criteria)
Do real tickets fit the data model, or do categories/priority levels need change?
Is the asset → impact flow (switch down → which servers/tickets) accurate with real data?
Do users adopt the PWA (mobile + desktop)?
What's missing for management reporting at the location level?
Output
Pilot feedback report → change list (data model changes, workflow changes, UX gaps) feeding the next iteration before scaling to remaining locations.
Milestone: Project: ITMS (id 100). Related card: #17.
## Objective
Launch ITMS as a **pilot at 1 SAPL location** to validate real-world fit before org-wide rollout. Goal of the pilot: learn **what changes are required** — in workflows, data model, and UX — when real IT staff and real assets/tickets replace the prototype seed.
## Pilot scope (1 location)
- [ ] Pick pilot location + pilot users (suggest Santosh + Vishal + 1-2 floor IT staff)
- [ ] Import real asset inventory for that location into CMDB (replaces seed data)
- [ ] Define ticket categories/priorities to match location's actual IT issues
- [ ] Run live: all IT issues at that location go through ITMS only (no parallel tracking)
- [ ] CMDB edges: record real switch → server → ticket dependencies
## What we're testing (success criteria)
1. Do real tickets fit the data model, or do categories/priority levels need change?
2. Is the asset → impact flow (switch down → which servers/tickets) accurate with real data?
3. Do users adopt the PWA (mobile + desktop)?
4. What's missing for management reporting at the location level?
## Output
**Pilot feedback report → change list** (data model changes, workflow changes, UX gaps) feeding the next iteration before scaling to remaining locations.
> Milestone: Project: ITMS (id 100). Related card: #17.
shridhar.sabat
added this to the Project: ITMS — IT Ticket & Asset Management milestone 2026-09-11 14:42:38 +05:30
Blocking a user prevents them from interacting with repositories, such as opening or commenting on pull requests or issues. Learn more about blocking a user.
Objective
Launch ITMS as a pilot at 1 SAPL location to validate real-world fit before org-wide rollout. Goal of the pilot: learn what changes are required — in workflows, data model, and UX — when real IT staff and real assets/tickets replace the prototype seed.
Pilot scope (1 location)
What we're testing (success criteria)
Output
Pilot feedback report → change list (data model changes, workflow changes, UX gaps) feeding the next iteration before scaling to remaining locations.